Rajasthan 22.5 MWp

22.5 MWp and 7.5 MWh, going up in the Thar.

A captive solar plant with battery storage designed in from the start, at Chamu in Jodhpur district — photographed in July 2026, mid-build.

Aerial view of the Chamu solar plant under construction — completed module rows on the left, bare mounting structures and trenching on the right, farmland beyond the boundary wall

Your browser could not start the film. The photographs below cover the same ground.

22.5 MWpDC capacity
15 MWAC capacity
7.5 MWhBattery storage
~55 acresSite area
38,136Modules at 590 Wp

A captive plant with a battery on the same interconnection.

Plant specification
LocationChamu, Jodhpur district, Rajasthan
DC capacity22.5 MWp
AC capacity15 MW
Battery storage7.5 MWh battery energy storage system (BESS), containerised lithium iron phosphate
Site areaApproximately 55 acres
Modules38,136 at 590 Wp
InvertersCentral inverters
Evacuation33 kV, via on-site step-up transformation
StructureCaptive structure, wheeled under open access — the consumer takes the power directly
StatusUnder construction
Why a battery

Solar stops at sunset. The load does not.

A factory that runs three shifts draws its heaviest load in the evening, exactly when a solar plant is producing nothing. Without storage, that block of demand goes back to the grid at the most expensive tariff of the day.

The battery charges on surplus generation through the middle of the day and discharges into the evening peak — so more of what the plant makes is actually consumed on site, and less of the expensive block is bought.

Why it is hard

Two plants sharing one point of interconnection.

Storage adds a bidirectional converter, an energy management system, a fire strategy and a protection scheme that has to satisfy the state inspectorate alongside the solar plant — not instead of it.

We engineer both sides, so the dispatch logic, the metering and the approvals are designed once, together, by the people who will also operate them.

On site

What 55 acres looks like halfway through.

Photographed in July 2026, while the plant was being built. Rows going in from one edge, mounting structures still bare at the other, and the electrical works running in parallel.

Aerial view of completed module rows meeting bare mounting structures, with an access track and cable trench running between them
The working edgeModules going in on one side, structures still bare on the other — the boundary moves across the site every week.
Sunlight glinting off a completed section of the array, rows running diagonally across sandy ground
Completed rows590 Wp modules on fixed-tilt structures, at a 7.3 metre table pitch.
Workers erecting module mounting structures in a row across sandy desert ground, steel purlins running to the horizon
Mounting structuresErected row by row across sand — our own crews, on a site with no infrastructure to start from.
Two wrapped battery containers standing on concrete plinths on site, with rows of mounting posts behind them
Battery containersDelivered and positioned — 7.5 MWh of lithium iron phosphate storage.
Aerial view of the electrical yard under construction, showing equipment plinths, foundations and delivered enclosures
The electrical yardPlinths and foundations for the conversion and switching equipment, set out before the plant reaches them.
Workers on the reinforced roof deck of the control room building during construction
Control roomBuilt in concrete on site — this is a plant meant to run for twenty-five years, not a temporary installation.

Photographed 28 July 2026. Every image on this page is this plant.

Why this project matters

This is the difference between an EPC and a platform.

Utility scale, not roof scale

22.5 MWp on 55 acres is a different discipline from a rooftop — land, survey, grading, an internal road network, a 33 kV interconnection and a state inspectorate approval. We do that work ourselves.

Storage as engineering, not a line item

Sizing a battery against a real load curve, and then integrating it, is where most solar companies stop and hand you a subcontractor. Storage is our own scope.

Built to be owned

An increasing share of what we build we also own and operate. That changes how you specify a plant — you stop optimising for handover and start optimising for year fifteen.

The plant is under construction and figures are as designed. Commercial terms, the offtaker and the financing structure are confidential. Generation and storage performance are governed by the availability, round-trip efficiency and capacity guarantees in the contract.

Start the conversation

Send us twelve months of bills.

Multi-megawatt load? Send twelve months of bills and we will tell you what a park like this one delivers to your meter. The analysis comes back free, with no commitment.